zaključna naloga Razvojno raziskovalnega programa I. stopnje Strojništvo
Ažbe Dimec (Author), Tomaž Berlec (Mentor)

Abstract

Zaradi večjega naročila kupca bo treba dvigniti produktivnost linije ali kupiti dodatno montažno linijo, kar bi bil prevelik finančni zalogaj. Dviga produktivnosti in krajšanja časa takta se lahko lotimo na različne načine. Za zelo učinkovite so se izkazale metode vitke proizvodnje in MTM analiza, s katero se analizirata čas dela in ergonomska razmestitev naprav in materiala. S temi ukrepi in analizami smo ugotovili, da lahko zahtevani takt kupca dosegamo s tremi delavci in želene kupčeve količine proizvajamo brez večjih dodatnih investicij na obstoječi liniji. Znižali smo čas takta na potrebnih 50 s/kos ter izboljšali izkoriščenost delavcev in naprav za 35 %.

Keywords

diplomske naloge;vitka proizvodnja;5S;SMED;Poka Yoke;MTM analiza;krajšanje;balansiranje;

Data

Language: Slovenian
Year of publishing:
Typology: 2.11 - Undergraduate Thesis
Organization: UL FS - Faculty of Mechanical Engineering
Publisher: [A. Dimec]
UDC: 658.51:005.935(043.2)
COBISS: 16565275 Link will open in a new window
Views: 1783
Downloads: 224
Average score: 0 (0 votes)
Metadata: JSON JSON-RDF JSON-LD TURTLE N-TRIPLES XML RDFA MICRODATA DC-XML DC-RDF RDF

Other data

Secondary language: English
Secondary title: Reducing the takt time of bezel group
Secondary abstract: Due to a higher customerʼs order, it will be necessary to raise the productivity of the line or to purchase an additional assembly line, which would be an excessive financial burden. Increasing productivity and shortening the takt time can be achieved in many ways. Lean production methods and MTM analysis, which analyzes the time of work and the ergonomic arrangement of devices and materials, have proved to be very effective. With these actions and analyzes, we found out that the required customerʼs takt time can be achieved with three workers and the desired customer quantity is produced without major additional investments on the existing line. We reduced the takt time to the required 50 s/pc and improved the utilization of workers and devices by 35%.
Secondary keywords: lean production;5S method;SMED;Poka Yoke;MTM analysis;reducing;balansing;
Type (COBISS): Final paper
Study programme: 0
Embargo end date (OpenAIRE): 2020-03-22
Thesis comment: Univ. v Ljubljani, Fak. za strojništvo
Pages: XIV, [36] f.
ID: 11070103
Recommended works:
, zaključna naloga Razvojno raziskovalnega programa I. stopnje Strojništvo
, zaključna naloga Razvojno raziskovalnega programa I. stopnje Strojništvo
, zaključna naloga Univerzitetnega študijskega programa I. stopnje Strojništvo - Razvojno raziskovalni program
, diplomsko delo visokošolskega strokovnega študija Organizacija in management delovnih procesov