diplomsko delo
Jan Škrablin (Author), Uroš Klanšek (Mentor)

Abstract

V diplomski nalogi so predstavljeni organizacija gradbišča ter tehnološki procesi rekonstrukcije in novogradnje obstoječega bencinskega servisa Celje. Prvi del naloge prikazuje splošne podatke o projektu, predvideni investiciji, prav tako pa tudi opiše obstoječe stanje in nakazuje na predvideno novo stanje objekta. V nadaljevanju sledi proučevanje pogojev za gradnjo objekta, in sicer se posveča proučevanju projektne dokumentacije, gradbene pogodbe, lokacijskih zmožnosti, klimatskih razmer in razpoložljivosti internih virov podjetja. Jedro diplomskega dela predstavlja organizacija gradbišča, ki obsega dimenzioniranje vseh začasnih prostorov, deponij gradbenega materiala in opreme, priključitev na komunalno oskrbo in opise notranjih ter zunanjih transportov. Zadnji del naloge opisuje procese rekonstrukcije in novogradnje objekta, kjer so natančno opisani vsi postopki gradnje, ki jih izvedemo, da zagotovimo optimalno opravljeno delo. V zaključku je prikazan načrt organizacije gradbišča.

Keywords

gradbeništvo;gradbena dela;organizacija gradbišča;dokumentacija;tehnološki procesi gradnje;

Data

Language: Slovenian
Year of publishing:
Typology: 2.11 - Undergraduate Thesis
Organization: UM FGPA - Faculty of Civil Engineering, Transportation Engineering and Architecture
Publisher: [J. Škrablin]
UDC: 69.05(043.2)
COBISS: 77778435 Link will open in a new window
Views: 434
Downloads: 87
Average score: 0 (0 votes)
Metadata: JSON JSON-RDF JSON-LD TURTLE N-TRIPLES XML RDFA MICRODATA DC-XML DC-RDF RDF

Other data

Secondary language: English
Secondary title: BUILDING SITE ORGANIZATION AND TECHNOLOGICAL PROCESSES OF CONSTRUCTION OF SERVICE STATION IN CELJE
Secondary abstract: The thesis presents the organization of the construction site and technological processes of reconstruction and new construction of the existing Celje petrol station. The first part of the assignment provides general information about the project, shows details about the investment, and gives a description of the existing situation as well as points to the planned new situation of the building. The next part studies the conditions of the construction, by examining the project documentation, the construction contract, climate conditions and the availability of internal resources of the company. The core of the thesis describes the organization of the construction site, which consists of dimensioning of all temporary spaces, the landfill of construction materials and equipment, the connection to the utility supply and the description of internal and external transports. In the final part, technological processes of reconstruction and new construction of the building, where all the construction procedures that were carried out for optimally done work, are described in detail. The conclusion shows the organizational plan of the construction site.
Secondary keywords: civil engineering;building works;construction site organization;documentation;technology for the construction;
Type (COBISS): Bachelor thesis/paper
Thesis comment: Univ. v Mariboru, Fak. za gradbeništvo, prometno inženirstvo in arhitekturo, Gradbeništvo
Pages: X, 78 f.