Model of the Sava river by Riverware program and the analysis of water pumping from the storage reservoir of HPP Medvode to the storage reservoir of HPP Mavčiče |
Secondary abstract: |
The first part of the graduation thesis presents the application of RiverWare program for the calculation of electricity production in the upper chain of Sava power stations, which comprises the following hydro power plants: Moste, Završnica, Mavčiče and Medvode. I made a model for the hydro power plant Moste, compared the results of power and electricity produced by RiverWare program, as well as power and energy produced by Sava power stations. The comparison showed too high deviations between the results. This was the reason, as well as inadequate methods of operational dynamics, that the RiverWare program package was demonstrated inadequate. In the second part I made a pumping model in Excel program. The model shows the operation of HPP Mavčiče with daily accumulation with pumping function. HPP Medvode operates in the run – of – river regime and in tandem with the Mavčiče HPP during peak power demand. The idea is that during night time, when electricity consumption is lower, water would be pumped from the compensating reservoir Zbilje into the upstream storage reservoir of the HPP Mavčiče. Pumping is carried out at inflow into the storage reservoir of the HPP Mavčiče from 15 m3 /s to 57 m3 /s. The comparison of electricity production from the model and the actual state showed that less energy is produced in relation to pumping; however, it is more expensive as the production could be increased in the peak time. |
Secondary keywords: |
software RiverWare;hydro power plant Mavčiče;hydro power plant Medvode;pumping model;peak energy;electricity production; |
File type: |
application/pdf |
Type (COBISS): |
Undergraduate thesis |
Thesis comment: |
Univ. Ljubljana, Fakulteta za gradbeništvo in geodezijo, Univerzitetni študij Vodarstva in komunalnega inženirstva |
Pages: |
XI, 79 str. |
Type (ePrints): |
thesis |
Title (ePrints): |
Izdelava modela Riverware za reko Savo in analiza možnosti črpanja iz akumulacije HE Medvode v akumulacijo HE Mavčiče |
Keywords (ePrints): |
gradbeništvo;diplomska dela;UNI;program RiverWare;hidroelektrarna Mavčiče;hidroelektrarna Medvode;model črpanja;vršna energija;proizvodnja električne energije; |
Keywords (ePrints, secondary language): |
software RiverWare;hydro power plant Mavčiče;hydro power plant Medvode;pumping model;peak energy;electricity production; |
Keywords (ePrints, secondary language): |
software RiverWare;hydro power plant Mavčiče;hydro power plant Medvode;pumping model;peak energy;electricity production; |
ID: |
8308117 |