Secondary language: |
English |
Secondary title: |
Review of the Execution of The Extension of the Sonček |
Secondary abstract: |
The thesis demonstrates a review of the running of the project titled The Extension of the Sonček Kindergarten in Semič. The author of the thesis monitored the course of the construction work up to the completion of its third phase. First, the organisation of the project and the conditions for the construction have been demonstrated. What follows is the presentation of the organisation of the technological construction process: it describes the methods of executing the individual phases of construction work, including technology, organisation and safety at the construction site. Furthermore, the thesis examines the use and the implementation of a safety plan at the construction site during construction work. The original action plan has been presented and compared with the actual course of work. In addition, it has been complemented by the photos which were taken by the author of the thesis during her daily observations of work at the construction site. The final stage of the thesis offers the author's comments and suggestions for improvement which are meant as guidelines for investors and construction companies managing similar construction projects in the future. |
Secondary keywords: |
graduation thesis;construction site;organisation;safety plan;action plan; |
File type: |
application/pdf |
Type (COBISS): |
Undergraduate thesis |
Thesis comment: |
Univ. v Ljubljani, Fak. za gradbeništvo in geodezijo |
Pages: |
XII, 78 str., [2] str. zganj. pril. |
Type (ePrints): |
thesis |
Title (ePrints): |
Review of the execution of the extension of the Sonček kindergarten in Semič project |
Keywords (ePrints): |
gradbišče;organizacija;varnostni načrt;terminski plan |
Keywords (ePrints, secondary language): |
construction site;organisation;safety plan;action plan |
Abstract (ePrints): |
V diplomski nalogi sem predstavila pregled izvajanja projekta Dozidava vrtca Sonček v Semiču. Spremljala sem potek gradbenih del do konca III. gradbene faze. Najprej sem prikazala organizacijo projekta, kjer sem preučila pogoje gradnje. Nato sem predstavila in preučila organizacijo tehnološkega procesa gradnje, opisala sem načine izvedbe posameznih del, ki vključujejo tehnologijo, organizacijo in varnost pri delu na gradbišču. V nadaljevanju sem preučila še uporabo varnostnega načrta na gradbišču in upoštevanje le-tega pri gradnji. Predstavila in primerjala sem osnovni terminski plan z dejanskim, in ga podkrepila s slikovnim gradivom, ki sem ga pridobila osebno z dnevnim opazovanjem poteka del na gradbišču. Nazadnje sem predstavila svoje pripombe in predloge izboljšav kot napotek investitorju in izvajalcem pri izvajanju tovrstnih projektov v bodoče. |
Abstract (ePrints, secondary language): |
The thesis demonstrates a review of the running of the project titled The Extension of the Sonček Kindergarten in Semič. The author of the thesis monitored the course of the construction work up to the completion of its third phase. First, the organisation of the project and the conditions for the construction have been demonstrated. What follows is the presentation of the organisation of the technological construction process: it describes the methods of executing the individual phases of construction work, including technology, organisation and safety at the construction site. Furthermore, the thesis examines the use and the implementation of a safety plan at the construction site during construction work. The original action plan has been presented and compared with the actual course of work. In addition, it has been complemented by the photos which were taken by the author of the thesis during her daily observations of work at the construction site. The final stage of the thesis offers the author's comments and suggestions for improvement which are meant as guidelines for investors and construction companies managing similar construction projects in the future. |
Keywords (ePrints, secondary language): |
construction site;organisation;safety plan;action plan |
ID: |
8312402 |