diplomsko delo univerzitetnega študijskega programa
Manca Glinšek Risman (Author), Uroš Klanšek (Mentor), Zoran Pučko (Co-mentor)

Abstract

Diplomsko delo obravnava problematiko operativnega planiranja gradnje objekta vrtca v Šentjurju. V teoretičnem delu so pojasnjeni osnovni pojmi in pomeni operativnega planiranja, terminskega planiranja ter statičnih in dinamičnih spremljajočih planov. Cilji diplomskega dela so določitev aktivnosti, določitev časov trajanja in določitev vrstnega reda izvajanja aktivnosti ter izdelava statičnih in dinamičnih spremljajočih planov. Sledi splošna predstavitev projekta z arhitekturnimi in tehničnimi značilnostmi predvidene gradnje. V analitičnem delu je predstavljen postopek terminskega planiranja. Rezultat tega je modificiran gantogram in mrežni diagram. V obliki tabel so izdelani tudi statični spremljajoči plani delovne sile, mehanizacije in materialov ter dinamični spremljajoči plani količin delovne sile mehanizacije materialov in finančnih sredstev v obliki histogramov, gantogramov ali tabel. V zaključku dela so povzeti rezultati in njihova ocena.

Keywords

operativno planiranje;terminski plani;statični plani;dinamični plani;gantogram;planiranje gradnje;diplomske naloge;

Data

Language: Slovenian
Year of publishing:
Typology: 2.11 - Undergraduate Thesis
Organization: UM FGPA - Faculty of Civil Engineering, Transportation Engineering and Architecture
Publisher: [M. Glinšek Risman]
UDC: 69.05(043.2)
COBISS: 17784342 Link will open in a new window
Views: 1620
Downloads: 171
Average score: 0 (0 votes)
Metadata: JSON JSON-RDF JSON-LD TURTLE N-TRIPLES XML RDFA MICRODATA DC-XML DC-RDF RDF

Other data

Secondary language: English
Secondary title: OPERATIONAL PLANNING OF CONSTRUCTION OF ŠENTJUR KINDERGARTEN UNIT IN HRUŠEVEC
Secondary abstract: The thesis deals with the problems of operational planning of construction of the Šentjur kindergarten unit in Hruševec. The theoretical part explains basic concepts and significance of operational planning and time scheduling, as well as static and dynamic accompanying plans. The aim of the thesis is to determine the activities, time periods and the order of implementation of activities, as well as to prepare static and dynamic accompanying plans. This is followed by a general presentation of the project with architectural and technical characteristics of the envisaged construction. The analytical part presents the time scheduling process. The results of that are a modified Gantt chart and a mesh chart. The tables contain the accompanying statistical manpower plans, mechanisation and materials, and the accompanying dynamic plans of quantities, manpower, mechanisation and financial resources in the form of histograms, Gantt charts or tables. The conclusion contains the summary of the results and their evaluation.
Secondary keywords: operational planning;time scheduling;static plans;dynamic plans;Gantt chart;construction planning;
URN: URN:SI:UM:
Type (COBISS): Undergraduate thesis
Thesis comment: Univ. v Mariboru, Fak. za gradbeništvo, Gradbeništvo
Pages: IX, 100 f., [23] f., [6] f. zanj. pril. z načrti
ID: 8727894
Recommended works:
, diplomsko delo univerzitetnega študijskega programa
, diplomsko delo visokošolskega študijskega programa
, diplomsko delo visokošolskega študijskega programa