diplomska naloga
Marjan Bradica (Author), Tomo Cerovšek (Mentor), Mitja Košir (Thesis defence commission member), Roman Kunič (Thesis defence commission member)

Abstract

V diplomskem delu sem poizkušal na primeru izgradnje projekta Novogradnja Fakultete za kemijo in kemijsko tehnologijo in Fakultete za računalništvo in informatiko prikazati, kako je potekala dejanska izbira in koordinacija posameznih podizvajalcev na gradbišču v podjetju Begrad, d. d., kjer sem delal kot vodja gradbišča. Opisal sem sámo organizacijo podjetja, kjer sem delal, njegov pristop pred pričetkom in med gradnjo projekta Fakultet FKKT in FRI. Za boljšo razumljivost in prikaz kompleksnosti sem tudi podrobno opisal projekt in njegovo strukturo pogodbenih razmerij. Izvedel sem tudi analizo izvedenih del na več načinov, ki so kasneje služili za primerjavo. V zaključku dela sem predlagal izboljšave ter naprednejše pristope glede na dejanske odločitve, ki smo jih izvajali tekom gradnje. Sledeči ukrepi bi lahko bistveno izboljšali proces izbire in koordinacije izvajalcev: elektronske izmere omogočajo bolj natančno in 80 % hitrejše določanje količin za pripravo povpraševanj za ponudbe in za izmere količin ob situacijah ter spremembah; informatizacija postopka izbire, boljša spremljava in koordinacija izvedbe, ki omogoča hitrejše in bolj transparentno izbiro podizvajalcev in izvedbo podizvajalskih del; izboljšanje koordinacije s podporo lokacijskih metod planiranja.

Keywords

gradbeništvo;diplomska naloga;VSŠ;gradbeni podizvajalci;planiranje;Microsoft Project;ciklogram;Vico Control;costx;elektronske izmere;

Data

Language: Slovenian
Year of publishing:
Typology: 2.11 - Undergraduate Thesis
Organization: UL FGG - Faculty of Civil and Geodetic Engineering
Publisher: [M. Bradica]
UDC: 004.6:624:69(043.2)
COBISS: 7295585 Link will open in a new window
Views: 1935
Downloads: 611
Average score: 0 (0 votes)
Metadata: JSON JSON-RDF JSON-LD TURTLE N-TRIPLES XML RDFA MICRODATA DC-XML DC-RDF RDF

Other data

Secondary language: English
Secondary title: Optimization of selection and coordination of subcotractors using model-locationbased methods
Secondary abstract: In my thesis I tried to explain and demonstrate the process of selection and coordination of subcontractors at the company Begrad, d.d., where I worked as a site manager. The project on which elaborate the thesis was the new building for the Faculty of Chemistry and Chemical Engineering (FKKT) and the Faculty of Engineering and Computer Science (FRI) in Ljubljana. I described the organizational structure of the company where I was employed, their approach prior and during the construction of the project Faculty FKKT and FRI. In order to improve the comprehensiveness and to show the complexity of the project, I described in detail the project and the structure of of contractual relations. I've also made an analysis of the subcontractors' works in several ways, which later served for a comparision. In the conclusion of my thesis I proposed the improvements and advancement of current approach in relation to the actual decisions that have been made during constructions. The proposed measures that could significantly improve the process of selection and coordination of subcontractors are as follows: Electronic measurements that enable more accurate and 80% faster quantity take-offs needed for monthly payments of subs and for measurements of changes; informatization of the selection process, monitoring and coordination to enable faster and more transparent selection of subcontractors and monitoring of works; enhanced coordination with the support for location-based planning methods.
Secondary keywords: sub-contractors;scheduling;Microsoft Project;flowline charts;Vico Control;costx;electronic measurements;
File type: application/pdf
Type (COBISS): Undergraduate thesis
Thesis comment: Univ. v Ljubljani, Fak. za gradbeništvo in geodezijo
Pages: X, 64 str., [25] str.pril.
ID: 9063652