diplomsko delo
Abstract
Diplomsko delo temelji na analizi trenutnega stanja in zaznavanju slabih napetostnih razmer v distribucijskem omrežju Elektra Celje, d. d., na širšem območju Vojnika. Na podlagi analiz so izvedene rešitve za ureditev slabih napetostnih razmer v omrežju, ki so s pomočjo programske opreme Gredos vključene v obravnavano omrežje. Preverjen je tudi njihov odziv. S pomočjo programske opreme Emona so predlagane rešitve za slabe napetostne razmere v omrežju preverjene tudi z ekonomskega vidika. Izbrana rešitev za slabe napetostne razmere v omrežju vsebuje določitev odgovorne osebe za izvedbo projekta, vsebino in parametre za nadaljnje projektiranje, podroben terminski plan izvedbe ter finančno ovrednotenje projekta z namenom planiranja sredstev v razvojnih načrtih družbe.
Keywords
električno omrežje;razdelilne transformatorske postaje;meritve enačrtovanje RTP;diplomske naloge;
Data
Language: |
Slovenian |
Year of publishing: |
2016 |
Typology: |
2.11 - Undergraduate Thesis |
Organization: |
UM FERI - Faculty of Electrical Engineering and Computer Science |
Publisher: |
G. Milanez |
UDC: |
621.317.727.1(043.2) |
COBISS: |
19984662
|
Views: |
1350 |
Downloads: |
183 |
Average score: |
0 (0 votes) |
Metadata: |
|
Other data
Secondary language: |
English |
Secondary title: |
DESIGN OF VOJNIK DISTRIBUTION TRANSFORMER SUBSTATION |
Secondary abstract: |
The thesis is based on an analysis of the current situation and the perception of low voltage conditions in the distribution network of Elektro Celje, d . d . , in the wider Vojnik area. Based on the Gredos software analysis performed, the solutions to remedy the low voltage conditions in the network are included in the present network. Verified is also their response. With the help of software Emona, proposed solutions to poor voltage conditions in the network are checked from an economic point of view. The chosen solution for poor power conditions in the network comprises determining the person responsible for the project implementation, content and parameters for further design, detailed timetable for implementation, and financial evaluation of the project with a view to planning resources in the development plans of the company. |
Secondary keywords: |
electricity grid;distribution transformer substation;planning of distribution transformer substation; |
URN: |
URN:SI:UM: |
Type (COBISS): |
Undergraduate thesis |
Thesis comment: |
Univ. v Mariboru, Fak. za elektrotehniko, računalništvo in informatiko, Elektrotehnika |
Pages: |
X, 88 f. |
ID: |
9161543 |