diplomsko delo visokošolskega študijskega programa
Abstract
V diplomskem delu smo proučevali gradnjo nadvoza 4 – 4 na avtocestnem odseku Beltinci–Lendava. Gradnja je potekala v dveh fazah: izvedba spodnje konstrukcije ter izvedba zgornje konstrukcije objekta. Spodnja konstrukcija je zajemala izvedbo temeljnih blazin, opornikov in stebrov. Zgornja konstrukcija pa je zajemala montažo jeklenega podpornega odra, montažo opaža za prekladno konstrukcijo, polaganje armature in kablov za prednapenjanje, betoniranje, napenjanje kablov, injektiranje prednapetih kablov, demontažo jeklene podporne konstrukcije, demontažo opaža ter opremo objekta.
Pri gradnji je bilo potrebno upoštevati terminske plane ter pravočasno dobavljati na gradbišče potrebne materiale. Pri vsem tem pa upoštevati, da bo objekt zgrajen kvalitetno, da bo zanesljiv, saj s tem zmanjšamo stroške vzdrževanja.
Keywords
nadvoz;gradnja;gradbišče;kvaliteta;
Data
Language: |
Slovenian |
Year of publishing: |
2009 |
Source: |
Maribor |
Typology: |
2.11 - Undergraduate Thesis |
Organization: |
UM FGPA - Faculty of Civil Engineering, Transportation Engineering and Architecture |
Publisher: |
[M. Šadl] |
UDC: |
625.7/.8:69.057.5(043.2) |
COBISS: |
13696278
|
Views: |
2747 |
Downloads: |
255 |
Average score: |
0 (0 votes) |
Metadata: |
|
Other data
Secondary language: |
English |
Secondary title: |
ǂThe ǂrealization of the overpass 4 - 4 on the highway section Beltinci - Lendava |
Secondary abstract: |
In this diploma work we thoroughly studied the construction of the overpass 4 – 4 on the highway section Beltinci–Lendava. The construction took place in two phases: the realization of the lower construction and the realization of the upper construction of the object. The lower construction included the construction of foundation pads, pillars and columns. The upper construction included the setting up of the steel scaffold, the setting up of panelling for the reloading construction, placing of the fittings and cables for the prestressing, concreting, cable stressing, injecting of prestressed cables, taking down the steel scaffold, taking down the panelling and the equipment of the object. Terminal plans as well as the punctual supply of necessary materials to the construction site had to be taken into consideration at construction. With all this it has to be considered that the object being built has quality and reliability and therefore the maintenance costs can be reduced. |
Secondary keywords: |
overpass;construction;construction site;quality; |
URN: |
URN:SI:UM: |
Type (COBISS): |
Undergraduate thesis |
Thesis comment: |
Univ. v Mariboru, Fak. za gradbeništvo |
Pages: |
VII, 68 f. |
Keywords (UDC): |
applied sciences;medicine;technology;uporabne znanosti;medicina;tehnika;engineering;technology in general;inženirstvo;tehnologija na splošno;civil engineering of land transport;railway engineering;highway engineering;tehnika kopenskih prometnih poti;gradnja železnic;cest in poti;highways in general;roads;carriageways;streets;rural and urban road systems;avtoceste na splošno;ceste;cestišča;ulice;podeželski in mestni cestni sistem;highway engineering;ceste;gradnja;applied sciences;medicine;technology;uporabne znanosti;medicina;tehnika;building (construction) trade;building materials;building practice and procedure;gradbeništvo;gradbeni materiali;gradbene obrti in dela; |
ID: |
986234 |