diplomska naloga
Povzetek
S hitrim napredkom, prihodom novih tehnologij in širjenjem ponudb storitev v turizmu, hotelski objekti hitro postanejo zastareli. Za uspeh in sledenje konkurenci ter vzdrževanjem nivoja kakovosti ponudb, se zato slednji pogosto odločajo za rekonstrukcije, renovacije in estetske ažuracije. Hotelski kompleksi navadno obratujejo v točno določenih sezonskih obdobjih (poletje, zima, ...). Časovni okvir izvedbe projekta rekonstrukcije je zato navadno zelo omejen, rok končanja del pa strikten in ne dopušča odstopanj. V diplomski nalogi prikažemo postopek rušenja hotelskega objekta, ki ga analiziramo tako s časovnega kot tudi s stroškovnega vidika.
Ključne besede
gradbeništvo;operativno gradbeništvo;diplomska naloga;VSŠ;GR;OG-MO;rušenje;ravnanje z odpadki;ločevanje odpadkov;odvoz ruševin;
Podatki
Jezik: |
Slovenski jezik |
Leto izida: |
2018 |
Tipologija: |
2.11 - Diplomsko delo |
Organizacija: |
UL FGG - Fakulteta za gradbeništvo in geodezijo |
Založnik: |
[N. Koščak] |
UDK: |
658.51:69.059.62:725(043.2) |
COBISS: |
8541793
|
Št. ogledov: |
832 |
Št. prenosov: |
351 |
Ocena: |
0 (0 glasov) |
Metapodatki: |
|
Ostali podatki
Sekundarni jezik: |
Angleški jezik |
Sekundarni naslov: |
Cost and time analysis of business building demolition |
Sekundarni povzetek: |
Due to fast progress, implementation of new technologies and expansion of tourist services, it can be observed that the hotels become obsolete in relatively short time. In order ot maintain business performance and keep up with the competition, the hotel management frequently decides to undertake reconstruction or renovation works. Hotel facilities usually operate in pre-determined season periods (summer, winter, %), therefore the timeframe available for completing the reconstruction is extremely limited, with strict deadline and does not allow deviations from the plan. The thesis presents the process of multi storey hotel building demolition. Theoretical background, including relevant legislature, is first presented. The case study % demolition of hotel building - is described. The project is analyzed and optimized, and the results are presented from the viewpoint of costs and time of completion. |
Sekundarne ključne besede: |
civil engineering;graduation thesis;demolition;waste management;waste separation;waste removal; |
Vrsta dela (COBISS): |
Diplomsko delo/naloga |
Študijski program: |
0 |
Konec prepovedi (OpenAIRE): |
1970-01-01 |
Komentar na gradivo: |
Univ. v Ljubljani, Fak. za gradbeništvo in geodezijo |
Strani: |
XI, 53 str. |
ID: |
10959350 |