diplomsko delo Visokošolskega strokovnega študijskega programa I. stopnje Strojništvo
Abstract
V podjetju, kjer se ukvarjajo z izdelavo ohišij za energetske transformatorje, se kljub povečanju proizvodnih kapacitet količina izdelkov ni bistveno povečala. Na oddelku sestave smo zato z orodji vitke proizvodnje in analizo toka vrednosti poskusili skrajšati pretočni čas izdelave podsklopa ohišja - stranice kotla. V prvem delu smo se seznanili s filozofijo vitke in metodami vitke proizvodnje, v drugem delu pa smo predstavili proizvodni proces izdelave transformatorskega ohišja. Proces izdelave stranice smo analizirali z metodo VSM. Izdelali smo diagram trenutnega stanja, ki smo ga z uporabo metod vitke proizvodnje in nekaterih tehnoloških rešitev izboljšali in izboljšan proces prikazali z diagramom idealnega stanja. Pretočni čas izdelave stranice smo skrajšali s 93,5 h na 21,33 h.
Keywords
diplomske naloge;vitka proizvodnja;analiza toka vrednosti;projektna proizvodnja;transformatorsko ohišje;varjena konstrukcija;
Data
Language: |
Slovenian |
Year of publishing: |
2019 |
Typology: |
2.11 - Undergraduate Thesis |
Organization: |
UL FS - Faculty of Mechanical Engineering |
Publisher: |
[T. Župevc] |
UDC: |
005.935:658.5:621.314(043.2) |
COBISS: |
16578587
|
Views: |
1048 |
Downloads: |
234 |
Average score: |
0 (0 votes) |
Metadata: |
|
Other data
Secondary language: |
English |
Secondary title: |
Lean process of manufacturing a power transformer housing |
Secondary abstract: |
The company that produces power transformer housings recently enlarged their production capacities, however, the production output did not increase significantly. Therefore, we tried to shorten the lead time of transformer tank wall assembly using methods of lean manufacturing and value stream analysis. In the first part, we learned about lean philosophy and the lean manufacturing methods. The second part is the presentation of the transformer housing production process. The tank wall assembly process was analysed using the VSM method. We created a current state VSM diagram, which we improved using methods of lean manufacturing and some technological solutions. The improved process was presented using an ideal state VSM diagram. Lead time of side wall assembly process was shortened from 93,5 h to 21,33 h. |
Secondary keywords: |
lean manufacturing;value stream analysis;project manufacturing;power transformer housing;welding construction; |
Type (COBISS): |
Bachelor thesis/paper |
Study programme: |
0 |
Embargo end date (OpenAIRE): |
1970-01-01 |
Thesis comment: |
Univ. v Ljubljani, Fak. za strojništvo |
Pages: |
XXII, 54 str. |
ID: |
11109718 |