diplomska naloga št.: 462/B-GR
Povzetek
V diplomski nalogi je opisana metoda linearnega planiranja pri linijskih projektih, metoda je predstavljena tudi z uporabo programskih orodji Microsoft Excel in Tilos. Kot primer projekta je obravnavan realen primer predora T2, ki bo izveden v sklopu projekta Drugi tir Divača – Koper. Analiziran je obstoječi terminski plan, ki je bil izdelan v programskem okolju Excel, dodatno pa je predstavljen tudi terminski plan, ki smo ga izdelali v s programskim paketom Tilos. Ker se predore pri nas izvaja po t.i. Novi avstrijski metodi, so predstavljeni njeni postopki in posebnosti. Predstavljene so tudi posebnosti pri sestavi pogodbe med naročnikom in izvajalcem ter njena določila, ki se zaradi nepredvidljivosti geologije pri izkopu, oblikujejo drugače kot pri večini ostalih pogodb.
Ključne besede
gradbeništvo;diplomske naloge;UNI;GR;B-GR;predorogradnja;NATM;linearno planiranje;Tilos;prilagodljiva gradbena pogodba;časovne norme;
Podatki
Jezik: |
Slovenski jezik |
Leto izida: |
2023 |
Tipologija: |
2.11 - Diplomsko delo |
Organizacija: |
UL FGG - Fakulteta za gradbeništvo in geodezijo |
Založnik: |
[G. Kump] |
UDK: |
624.19:658.513.3/.4(043.2) |
COBISS: |
178361859
|
Št. ogledov: |
176 |
Št. prenosov: |
12 |
Ocena: |
0 (0 glasov) |
Metapodatki: |
|
Ostali podatki
Sekundarni jezik: |
Angleški jezik |
Sekundarni naslov: |
Developing a timetable for the construction of the tunnel based on the Linear Scheduling Method |
Sekundarni povzetek: |
The thesis describes Linear Scheduling Method used for linear projects, method is presented using Microsoft Excel and Tilos. Tunnel T2 from project Drugi tir Divača – Koper is taken as a real case study. The existing schedule, which was produced in Excel, is analysed, and the schedule produced in Tilos is presented in addition. As the tunnels in Slovenia are being made according to the so-called New Austrian Tunneling Method, its procedures are described in this paper, as well as tendering and costing procedures at contract drafting, as unpredictability in geology causeses diffrences between common contract practices and contracts in tunnel engineering. |
Sekundarne ključne besede: |
graduation thesis;civil engineering;tunneling;NATM;linear project planning;Tilos;flexible construction contract; |