Construction schedule and partner analysis: a pipeline case study |
Sekundarni povzetek: |
The thesis presents the construction process of the pipeline R25D Šentrupert-Šoštanj with
emphasis on project schedule analysis. The presented case is a challenging project and its
execution depends upon several factors. The thesis also proposes possible solutions to
mitigate the problems and delays.
The first part is dedicated to systematical overview of all procedures, processes and
documents required in construction of the structure under consideration. The overview
reflects the current state of Slovenian construction legislation.
The core of the thesis is presented in the second part, where the case study – pipeline
construction is presented. The planned schedule is compared to as-built schedule. Contractual
relations and supply chain are presented and discussed. The analysis shows that quality
schedule plan is of key importance if successful completion of the project is desired.
Further, the results show that during execution of works, a large number of factors causing
delays are present. The factors can be attributed to various causes of both external and internal
nature. |
Sekundarne ključne besede: |
construction;schedule plan;pipeline;project participants; |
Vrsta datoteke: |
application/pdf |
Vrsta dela (COBISS): |
Diplomsko delo |
Komentar na gradivo: |
Univ. v Ljubljani, Fak. za gradbeništvo in geodezijo |
Strani: |
XX f., 111 str., pril. |
Vrsta dela (ePrints): |
thesis |
Naslov (ePrints): |
Analiza gradbenega projekta s poudarkom na udeležencih: primer gradnje plinovoda |
Ključne besede (ePrints): |
gradbeništvo;diplomska dela;UNI;graditev;terminski plan;plinovod;projektni udeleženci; |
Ključne besede (ePrints, sekundarni jezik): |
construction;schedule plan;pipeline;project participants; |
Ključne besede (ePrints, sekundarni jezik): |
construction;schedule plan;pipeline;project participants; |
ID: |
8309563 |