Planiranje z omejenimi viri - študij primera z uporabo Primavera Project Planner Version 3.1

Ključne besede

gradbeništvo;diplomska dela;UNI;komunalna smer;planiranje z omejenimi resursi;programska orodja;kontrola projekta;

Podatki

Jezik: Slovenski jezik
Leto izida:
Izvor: Ljubljana
Tipologija: 2.11 - Diplomsko delo
Organizacija: UL FGG - Fakulteta za gradbeništvo in geodezijo
Založnik: [Ž. Babnik]
UDK: 004.42:65.012.2.69(043.2)
COBISS: 3180897 Povezava se bo odprla v novem oknu
Št. ogledov: 1926
Št. prenosov: 867
Ocena: 0 (0 glasov)
Metapodatki: JSON JSON-RDF JSON-LD TURTLE N-TRIPLES XML RDFA MICRODATA DC-XML DC-RDF RDF

Ostali podatki

Sekundarni jezik: Angleški jezik
Sekundarni naslov: Resource constrained scheduling - a casa study using Primavera Project Planner Version 3.1
Sekundarni povzetek: In the spring semester of the academic year 2005/06 I took part in the Socrates Erasmus student exchange, writing my graduation thesis at the Project Management Centre at Istanbul Technical University. In this thesis I will present the process of planning along with its basic properties and methods, which have to be used when planning a project in the construction sector, using the expanded Critical Path Method. I included some theoretical background of resource scheduling and its possibility of using it with modern software tools, which is presented on a real project prepared by using Primavera Project Planner Version 3.1, a modern programme for planning and managing projects. The techniques I dealt with are levelling, allocation, cumulation, aggregation and smoothing. In order to control the project, the Earned value analysis is presented as well. Apart from all the aforementioned methods and techniques, I also decided to portray how the professionals in construction should use these techniques with modern software tools for managing and planning the project during its life, including the reports that are made right after a particular plan is finished, as well as other reports compiled during the project, if the project contains all necessary data. These reports are: schedule, resource/cost control, resource/cost loading, productivity, cash flow, earned value, tabular resource/cost and matrix reports made with P3. In the end, the solutions for sending and sharing project data via the web or local servers between the members of a project team, as well as the responsibilities of the latter for resource scheduling and managing the project using P3 are depicted.
Sekundarne ključne besede: resource constrained scheduling;PM software tools;project control;
Vrsta datoteke: application/pdf
Vrsta dela (COBISS): Diplomsko delo
Komentar na gradivo: Univ. Ljubljana, Fakulteta za gradbeništvo in geodezijo, Oddelek za gradbeništvo, Univerzitetni študij, Komunalna smer
Strani: XVIII, 88 str., pril.
Vrsta dela (ePrints): thesis
Naslov (ePrints): Planiranje z omejenimi viri - študij primera z uporabo Primavera Project Planner Version 3.1
Ključne besede (ePrints): gradbeništvo;diplomska dela;UNI;komunalna smer;planiranje z omejenimi resursi;programska orodja;kontrola projekta;
Ključne besede (ePrints, sekundarni jezik): resource constrained scheduling;PM software tools;project control;