diplomska naloga
Povzetek
Diplomska naloga obravnava potek izvedbe javnega naročila na področju gradenj vse od
identifikacije potrebe po investiciji s strani naročnika, pa do priprave ponudbe s strani
ponudnika.
Predstavljena je zakonodaja, ki ureja javno naročanje in podrobneje so analizirana določila,
ki znatno vplivajo na določanje prodajne cene. Posebej je obravnavana ocenjena vrednost
javnega naročila, ki jo naročnik lahko objavi na portalu javnih naročil. S pomočjo vprašalnika
in s statistično analizo podatkov iz portala javnih naročil je analiziran vpliv objave ocenjene
vrednosti na določanje prodajne cene s strani ponudnikov.
Popis del je sestavni del razpisne dokumentacije in je osnova za kalkuliranje stroškov
gradbenih del. Analizirana je sestava popisa del in evidentirane so pomanjkljivosti, ki vplivajo
na kakovost popisa.
Tradicionalna metoda kalkuliranja gradbenih del, ki je obravnavana v slovenski literaturi,
sloni na popisu del. Izračun ponudbene cene izhaja iz izračuna stroškov po postavkah iz
popisa. V diplomski nalogi je metoda predstavljena na primeru iz prakse. Na istem primeru je
predstavljena tudi t.i. netradicionalna metoda, ki se v praksi pojavlja kot alternativa.
Predstavljene so prednosti te metode in razlogi zakaj se v praksi iščejo alternative
tradicionalnemu načinu gradbenih kalkulacij.
Ključne besede
gradbeništvo;diplomska naloga;UNI;javno naročilo;razpisna dokumentacija;gradbene kalkulacije;popis del;lastna cena;prodajna cena;
Podatki
Jezik: |
Slovenski jezik |
Leto izida: |
2016 |
Tipologija: |
2.11 - Diplomsko delo |
Organizacija: |
UL FGG - Fakulteta za gradbeništvo in geodezijo |
Založnik: |
[N. Filipin] |
UDK: |
005.5:69(497.4)(043.2) |
COBISS: |
7378785
|
Št. ogledov: |
2154 |
Št. prenosov: |
606 |
Ocena: |
0 (0 glasov) |
Metapodatki: |
|
Ostali podatki
Sekundarni jezik: |
Angleški jezik |
Sekundarni naslov: |
Public procurement in construction: Analysis of the process from tender documentation to the preparation of the offer |
Sekundarni povzetek: |
The thesis deals with the execution of a public tender in the field of construction. The
analysis starts by the identification of the need for investment by the customer, and ends with
the preparation of the offer by the bidder.
It presents the legislation concerning public procurement, and it analyses in detail the
provisions that have a significant impact on the determination of the selling price. The thesis
specifically deals with the estimated value of the public tender that may be published on the
procurement portal. A questionnaire and statistical analysis are used to verify the impact of
published estimates on the act of fixing the prices by suppliers.
Bill of quantities (BoQ) is an essential part of the tender documentation and the basis for
costing of construction works. In the thesis, the composition of a bill of quantities is analyzed
and the deficiencies that affect the quality of it are evidenced.
The traditional method of construction cost estimation, presented in the Slovenian literature,
is based on the bill of quantities. In this method the calculation of the tender price is based on
calculation of cost for each item in the bill of quantities. In the thesis the method is presented
on a case study. For the same case study the so-called non-traditional method is used as an
alternative that is used in practice. In the conclusion the advantages of the non-traditional
method are exposed, and consequently reasons are obtained, for why alternatives to the
traditional way of construction cost estimation are used. |
Sekundarne ključne besede: |
graduation thesis;public procurement;tender documentation;construction cost estimation;production cost;selling price; |
Vrsta datoteke: |
application/pdf |
Vrsta dela (COBISS): |
Diplomsko delo |
Komentar na gradivo: |
Univ. v Ljubljani, Fak. za gradbeništvo in geodezijo |
Strani: |
X, 80 str., 1 pril. |
ID: |
9122956 |