diplomska naloga
Jasna Slemenšek (Avtor), Jana Šelih (Mentor), Tomo Cerovšek (Član komisije za zagovor), Maruška Šubic Kovač (Član komisije za zagovor)

Povzetek

Diplomsko delo analizira potek izgradnje poslovne stavbe s časovnega in stroškovnega vidika. Izvedli smo časovno analizo in primerjavo med pogodbenim ter operativnim terminskim planom in dejansko izvedbo gradbenega projekta od uvedbe v delo do primopredaje. Navedeni so razlogi za odstopanja dejanskega izvajanja del od pogodbenega terminskega plana. Za izvajalca gradbenih del je nujno, da pri dejanski izvedbi sledi pogodbenemu terminskemu planu. Narejena je bila tudi stroškovna analiza za betonska, železokrivska, zidarska dela in opaževanje ter fasadne odre. V analizi je narejena primerjava med kalkulacijo, na podlagi ponudbenih cen, in pokalkulacijo, kjer so upoštevane dejanske cene vgrajenih količin. Na koncu so navedeni še razlogi za povišanje pogodbene cene pri projektu.

Ključne besede

gradbeništvo;diplomska naloga;gradbena pogodba;gradnja;terminski plan;kalkulacija;

Podatki

Jezik: Slovenski jezik
Leto izida:
Tipologija: 2.11 - Diplomsko delo
Organizacija: UL FGG - Fakulteta za gradbeništvo in geodezijo
Založnik: [J. Slemenšek]
UDK: 005.8:725.1(497.4)(043.2)
COBISS: 7823457 Povezava se bo odprla v novem oknu
Št. ogledov: 3171
Št. prenosov: 549
Ocena: 0 (0 glasov)
Metapodatki: JSON JSON-RDF JSON-LD TURTLE N-TRIPLES XML RDFA MICRODATA DC-XML DC-RDF RDF

Ostali podatki

Sekundarni jezik: Angleški jezik
Sekundarni naslov: Time and cost analysis of commercial building construction
Sekundarni povzetek: This thesis analyses the construction course of a commercial building from two aspects: time and cost. A time analysis and a comparison between a contract term plan and an executive term plan as well as the actual execution of the constructional project from the start of the construction until the handover and acceptance are being presented. Reasons for the deviation from the constructional work term plan are stated. It is of the uttermost importance for the contractor to follow the term plan stated in the construction contract. A cost analysis for concrete, metal and mason work, as well as panelling and scaffolding is performed. The analysis contains a comparison between an offer-based calculation and an after-calculation, which complies with the actual cost of used quantities. Reasons for the increase of the contract price of a project are stated at the end.
Sekundarne ključne besede: graduation thesis;civil engineering;construction contract;construction;term plan;calculation;
Vrsta datoteke: application/pdf
Vrsta dela (COBISS): Diplomsko delo
Komentar na gradivo: Univ. v Ljubljani, Fak. za gradbeništvo in geodezijo
Strani: X, 54 str.
ID: 9234924