diplomsko delo univerzitetnega študijskega programa
Abstract
V diplomski nalogi je predstavljena možnost gradnje male hidroelektrarne na odseku potoka Hudinja v občini Vitanje. Območje spada v ekološko pomembno območje in območje naravnih vrednot, zato zanj veljajo posebni predpisi in standardi, ki jih je treba upoštevati. Kljub tehnični izvedljivosti in upoštevanju predpisov, gradnja v tem delu zaradi mnenja Zavoda Republike Slovenije za varstvo narave ni možna.
Izbrali smo lokacijo zajezitve vode in lokacijo strojnice ter za poseg v naravo pridobili posamezna strokovna mnenja vladnih služb. Analizirali smo pretok potoka, ekološko sprejemljivi pretok in analizirali tehnično rešitev elektrarne. Predstavili smo zahteve po izgradnji ribje steze ter napravili primer izračuna le-te. Izračunali smo investicijske stroške elektrarne, prihodke iz prodaje ter predstavili dobo povračila investicije oziroma ekonomsko upravičenost izgradnje.
Keywords
proizvodnja električne energije;hidroelektrarne;mala hidroelektrarna;varovanje okolja;stroški;ekonomska upravičenost;gradnja;
Data
Language: |
Slovenian |
Year of publishing: |
2011 |
Source: |
Maribor |
Typology: |
2.11 - Undergraduate Thesis |
Organization: |
UM FERI - Faculty of Electrical Engineering and Computer Science |
Publisher: |
[J. Gorečan] |
UDC: |
621.311.21(043.2) |
COBISS: |
15965974
|
Views: |
4018 |
Downloads: |
499 |
Average score: |
0 (0 votes) |
Metadata: |
|
Other data
Secondary language: |
English |
Secondary title: |
Small hydro power plant on stream Hudinja |
Secondary abstract: |
The diploma paper presents the possibility of building a small hydroelectric power plant on the section of the brook Hudinja in the municipality Vitanje. The area falls within the ecologically significant areas and represents an area of natural values, and therefore it is subject to specific regulations and standards which must be complied. Despite the technical feasibility and regarding the regulations, building in this area – according to the Institute of the Republic of Slovenia for Nature Conservation – is not possible.
We have chosen the location of the water reservoir and the location of the machine house, and we have collected individual professional opinions of the government department about the interference to nature. We have examined the flow of the brook, the ecological acceptable flow and analysed the technical solution of the power plant. We have presented a request for the construction of a fish track and we have given an example of its calculation. We have made calculations of the power plant investment costs, the income from sales and we have also presented the period of return on this investment, namely the economic justification of the construction. |
Secondary keywords: |
power generation;hydropower plants;small hydroelectric power plant;environmental protection;costs;economics;construction; |
URN: |
URN:SI:UM: |
Type (COBISS): |
Undergraduate thesis |
Thesis comment: |
Univ. v Mariboru, Fak. za elektrotehniko, računalništvo in informatiko |
Pages: |
XVI, 178 f. |
Keywords (UDC): |
applied sciences;medicine;technology;uporabne znanosti;medicina;tehnika;engineering;technology in general;inženirstvo;tehnologija na splošno;mechanical engineering in general;nuclear technology;electrical engineering;machinery;strojništvo;electrical engineering;elektrotehnika; |
ID: |
1016595 |