diplomsko delo univerzitetnega študijskega programa
Janko Gorečan (Avtor), Jože Pihler (Mentor), Gorazd Štumberger (Komentor)

Povzetek

V diplomski nalogi je predstavljena možnost gradnje male hidroelektrarne na odseku potoka Hudinja v občini Vitanje. Območje spada v ekološko pomembno območje in območje naravnih vrednot, zato zanj veljajo posebni predpisi in standardi, ki jih je treba upoštevati. Kljub tehnični izvedljivosti in upoštevanju predpisov, gradnja v tem delu zaradi mnenja Zavoda Republike Slovenije za varstvo narave ni možna. Izbrali smo lokacijo zajezitve vode in lokacijo strojnice ter za poseg v naravo pridobili posamezna strokovna mnenja vladnih služb. Analizirali smo pretok potoka, ekološko sprejemljivi pretok in analizirali tehnično rešitev elektrarne. Predstavili smo zahteve po izgradnji ribje steze ter napravili primer izračuna le-te. Izračunali smo investicijske stroške elektrarne, prihodke iz prodaje ter predstavili dobo povračila investicije oziroma ekonomsko upravičenost izgradnje.

Ključne besede

proizvodnja električne energije;hidroelektrarne;mala hidroelektrarna;varovanje okolja;stroški;ekonomska upravičenost;gradnja;

Podatki

Jezik: Slovenski jezik
Leto izida:
Izvor: Maribor
Tipologija: 2.11 - Diplomsko delo
Organizacija: UM FERI - Fakulteta za elektrotehniko, računalništvo in informatiko
Založnik: [J. Gorečan]
UDK: 621.311.21(043.2)
COBISS: 15965974 Povezava se bo odprla v novem oknu
Št. ogledov: 4018
Št. prenosov: 499
Ocena: 0 (0 glasov)
Metapodatki: JSON JSON-RDF JSON-LD TURTLE N-TRIPLES XML RDFA MICRODATA DC-XML DC-RDF RDF

Ostali podatki

Sekundarni jezik: Angleški jezik
Sekundarni naslov: Small hydro power plant on stream Hudinja
Sekundarni povzetek: The diploma paper presents the possibility of building a small hydroelectric power plant on the section of the brook Hudinja in the municipality Vitanje. The area falls within the ecologically significant areas and represents an area of natural values, and therefore it is subject to specific regulations and standards which must be complied. Despite the technical feasibility and regarding the regulations, building in this area – according to the Institute of the Republic of Slovenia for Nature Conservation – is not possible. We have chosen the location of the water reservoir and the location of the machine house, and we have collected individual professional opinions of the government department about the interference to nature. We have examined the flow of the brook, the ecological acceptable flow and analysed the technical solution of the power plant. We have presented a request for the construction of a fish track and we have given an example of its calculation. We have made calculations of the power plant investment costs, the income from sales and we have also presented the period of return on this investment, namely the economic justification of the construction.
Sekundarne ključne besede: power generation;hydropower plants;small hydroelectric power plant;environmental protection;costs;economics;construction;
URN: URN:SI:UM:
Vrsta dela (COBISS): Diplomsko delo
Komentar na gradivo: Univ. v Mariboru, Fak. za elektrotehniko, računalništvo in informatiko
Strani: XVI, 178 f.
Ključne besede (UDK): applied sciences;medicine;technology;uporabne znanosti;medicina;tehnika;engineering;technology in general;inženirstvo;tehnologija na splošno;mechanical engineering in general;nuclear technology;electrical engineering;machinery;strojništvo;electrical engineering;elektrotehnika;
ID: 1016595
Priporočena dela:
, diplomsko delo univerzitetnega študijskega programa
, diplomsko delo univerzitetnega študijskega programa 1. stopnje
, magistrsko delo
, diplomska naloga univerzitetnega študijskega programa
, diplomsko delo