magistrsko delo
Abstract
Magistrska naloga, mala hidroelektrarna na reki Sopoti, je izdelana z namenom in ciljem ugotoviti smiselnost koriščenja tega vodnega vira. Izbira in obdelava te teme me je pritegnila iz tega razloga, ker je tu nekoč že obratovala mala hidroelektrarna, ki pa so jo približno pred dvajsetimi leti ustavili. V nalogi sem zajel in predstavil zakonodajo in postopke, ki so potrebni pri izvedbi takega projekta. Na splošno je, moja ugotovitev, da so v naši državi ti administrativni postopki preveč zahtevni, še bolj pa komplicirano zastavljeni. Na koncu naloge sem v ekonomski analizi prikazal in dokazal, z določenimi metodami , da je smiselno postaviti tako elektrarno in jo koristiti kot stalen obnovljiv vir.
Keywords
mala hidroelektrarna;vodne turbine;obnovljivi viri;vodna energija;reka Sopota;referenčni stroški;deklaracija;modra energija;zelena energija;projektna dokumentacija;
Data
Language: |
Slovenian |
Year of publishing: |
2011 |
Source: |
Krško |
Typology: |
2.09 - Master's Thesis |
Organization: |
UM FE - Faculty of Energetics |
Publisher: |
[P. Žnidaršič] |
UDC: |
621.311.2(043.3) |
COBISS: |
1024052060
|
Views: |
5889 |
Downloads: |
714 |
Average score: |
0 (0 votes) |
Metadata: |
|
Other data
Secondary language: |
English |
Secondary title: |
Small hydro power plant at river Sopota |
Secondary abstract: |
The master's thesis The small hydro plant on the riverSopota ; (Mala hidroelektrarna na reki Sopoti) is written with an aim to asses the benefits of employing the previously mentioned hydro plant as anenergy source. The theme and its analysis intrigued me due to the fact that thepower plant used to be operational but closed its doors nearly twenty years ago. The thesis comprises of the presentation of the legislation and the legislativeprocedures needed for the execution of such a project. I have come to the conclusion that these administrative procedures are too overwhelming in our country and moreover, complicated. In the economic analysis at the end of the thesis I have demonstrated and proventhat the setting up and employment of such a hydro plant as a renewable energysource is reasonable. |
Secondary keywords: |
small hydro power plant;water turbine;hydropower;Sopota;reference costs;declaration;blue energy;green energy;project documentation; |
URN: |
URN:SI:UM: |
Type (COBISS): |
Master's thesis/paper |
Thesis comment: |
Mag. delo, Univ. Maribor, Fakulteta za energetiko |
Pages: |
IX, 66, 5 f. |