diplomsko delo
Darko Debelak (Avtor), Uroš Klanšek (Mentor), Zoran Pučko (Komentor)

Povzetek

V diplomski nalogi je predstavljena organizacija gradbišča in terminsko planiranje hale Agroteh Vrbek v Šentjurju. Najprej je podan opis lokacije, funkcionalne zasnove in tehničnih značilnosti novega objekta. V drugem delu preučimo pogoje za gradnjo, kar zajema proučitev dokumentacije o lokaciji, gradbenega dovoljenja, gradbene pogodbe, razpoložljiva delovna sredstva, kadrovske možnosti, možnost nabave materiala ter organizacijske možnosti na lokaciji gradbišča. Tretji del obravnava organizacijo gradbišča, ki zajema opis gradbišča, dimenzioniranje začasnih objektov, deponij, inštalacij, popis pripravljalnih in zaključnih del ter shemo organizacije gradbišča. Zadnji del predstavlja terminsko planiranje gradnje objekta v obliki modificiranega gantograma in mrežnega diagrama.

Ključne besede

gradbeništvo;organizacija gradbišča;terminsko planiranje;diplomske naloge;

Podatki

Jezik: Slovenski jezik
Leto izida:
Tipologija: 2.11 - Diplomsko delo
Organizacija: UM FGPA - Fakulteta za gradbeništvo, prometno inženirstvo in arhitekturo
Založnik: [D. Debelak]
UDK: 69.05+658.513(043.2)
COBISS: 21462038 Povezava se bo odprla v novem oknu
Št. ogledov: 965
Št. prenosov: 305
Ocena: 0 (0 glasov)
Metapodatki: JSON JSON-RDF JSON-LD TURTLE N-TRIPLES XML RDFA MICRODATA DC-XML DC-RDF RDF

Ostali podatki

Sekundarni jezik: Angleški jezik
Sekundarni naslov: Building site organization and construction time scheduling for facility Agroteh Vrbek in Šentjur
Sekundarni povzetek: The thesis presents the organization of construction site and a construction time scheduling for hall Agroteh Vrbek in Šentjur. First is a description of the location, functional concept and technical features of the new building. In the second part we are examing the condition for the construction, which include examination the documentation of location, building permit, construction contracts, available labor resources, possibility of human resources, possibility of purchasing material and organization possibilities at the location of the construction site. The third part deals with the organization of the construction site, which includes a description of the site, design of temporary structures, depots, installation, list of preparation and finishing works and site organization scheme. The last part represent construction time scheduling of construction in the form of modified grantt chart and network diagram.
Sekundarne ključne besede: civil engineering;organization of the construction site;construction time scheduling;
URN: URN:SI:UM:
Vrsta dela (COBISS): Diplomsko delo/naloga
Komentar na gradivo: Univ. v Mariboru, Fak. za gradbeništvo, prometno inženirstvo in arhitekturo, Gradbeništvo
Strani: XI, 94 f., [4] zganj. pril. z načrti
ID: 10916705