Management of construction deviations based on FIDIC contract conditions |
Sekundarni povzetek: |
Construction is a challenging and long-term process during which situations causing deviations and
disagreements between the contracting parties might occur. One of the possible reasons for such
occurrences is a poorly prepared construction contract. By signing it the constructor binds himself to
carry out the work whereas the customer binds himself to pay the constructor a certain price for the
given service. It is for this reason that the contract should be written carefully and thoughtfully.
My diploma thesis is divided into two parts. In the first part I will focus on theoretical references and
general terms which are used to regulate contracting relations between the parties and are applicable to
the Slovenian legislation. How contracting relations are regulated by the international organisation
FIDIC will also be presented. Firstly I will provide a description of the general FIDIC conditions, their
applicability and their development through history as well as their compatibility with the Slovenian
legislation.
In the second part of the thesis a detailed presentation of contracting relations from the FIDIC's Red
Book will be given. These prove themselves to be a more effective, inexpensive and faster way of
solving the deviations that occur during construction. To enable a faster and easier reading of these
procedures, I created a graphical representation of the diagrams which present the processes of
individual events connected with a regular occurrence of deviations. The final finding is that the
diagrams enable the overall review of all the procedures, reading them becomes faster and more
comprehensible. |
Sekundarne ključne besede: |
graduation thesis;civil engineering;construction contract;FIDIC;Employer;Contractor;Engineer; |
Vrsta datoteke: |
application/pdf |
Vrsta dela (COBISS): |
Diplomsko delo |
Komentar na gradivo: |
Univ. v Ljubljani, Fak. za gradbeništvo in geodezijo |
Strani: |
XIV, 74 str., [25] str. pril. |
Vrsta dela (ePrints): |
thesis |
Naslov (ePrints): |
Management of construction deviations based on FIDIC contract conditions |
Ključne besede (ePrints): |
gradbena pogodba;FIDIC;naročnik;izvajalec;inženir |
Ključne besede (ePrints, sekundarni jezik): |
construction contract;FIDIC;Employer;Contractor;Engineer |
Povzetek (ePrints): |
Gradnja je zahteven in dolgotrajen proces pri katerem prihaja velikokrat do dogodkov, ki povzročijo
odstopanja, katera lahko vodijo do spora med pogodbenimi strankami. Vzroke za to lahko med
drugim iščemo tudi v slabo pripravljeni gradbeni pogodbi. S podpisom gradbene pogodbe se namreč
izvajalec zaveže, da bo dela izvedel, naročnik pa se zaveže, da mu bo za to delo plačal določeno ceno,
zato mora biti gradbena pogodba sestavljena skrbno in premišljeno.
Diplomsko nalogo razdelimo na dva dela. V prvem delu diplome se tako posvetimo teoretičnim
izhodiščem, kjer se osredotočimo na splošne pojme pravnih virov, ki urejajo pogodbena razmerja med
strankami v skladu z našo zakonodajo, v nadaljevanju pa predstavimo, kako ta razmerja ureja
mednarodna organizacija FIDIC. Najprej sledi opis splošnih pogojev FIDIC, njihova uporabnost in
razvoj skozi zgodovino, njihovo poznavanje pri nas ter skladnost z našo zakonodajo.
V drugem delu naloge podrobno predstavimo pogodbene odnose po Rdeči knjigi FIDIC, ki se izkažejo
kot učinkovitejši, hitrejši in cenejši način usklajevanja odstopanj pri gradnji med pogodbenimi
strankami. Za lažje in hitrejše branje teh postopkov izdelamo grafičen prikaz diagramov poteka
procesov za posamezne dogodke oziroma okoliščine pri katerih najpogosteje prihaja do možnih
odstopanj. Ugotovimo, da nam diagrami bistveno poenostavijo celoten pregled teh postopkov, branje
je hitrejše in bolj razumevajoče. |
Povzetek (ePrints, sekundarni jezik): |
Construction is a challenging and long-term process during which situations causing deviations and
disagreements between the contracting parties might occur. One of the possible reasons for such
occurrences is a poorly prepared construction contract. By signing it the constructor binds himself to
carry out the work whereas the customer binds himself to pay the constructor a certain price for the
given service. It is for this reason that the contract should be written carefully and thoughtfully.
My diploma thesis is divided into two parts. In the first part I will focus on theoretical references and
general terms which are used to regulate contracting relations between the parties and are applicable to
the Slovenian legislation. How contracting relations are regulated by the international organisation
FIDIC will also be presented. Firstly I will provide a description of the general FIDIC conditions, their
applicability and their development through history as well as their compatibility with the Slovenian
legislation.
In the second part of the thesis a detailed presentation of contracting relations from the FIDIC's Red
Book will be given. These prove themselves to be a more effective, inexpensive and faster way of
solving the deviations that occur during construction. To enable a faster and easier reading of these
procedures, I created a graphical representation of the diagrams which present the processes of
individual events connected with a regular occurrence of deviations. The final finding is that the
diagrams enable the overall review of all the procedures, reading them becomes faster and more
comprehensible. |
Ključne besede (ePrints, sekundarni jezik): |
construction contract;FIDIC;Employer;Contractor;Engineer |